Hagsätra Ice Hall Project: Delays, Budget Issues, Smaller Size
The Real Estate Committee approved a status report for the Hagsätra ice and sports hall project at Hagsätra IP. Despite a positive construction start, the project faces budget and procurement challenges, a reduced area of approximately 2,000 square meters, and a delay of about one year. The committee requests a more detailed follow-up on remaining risks, rental consequences, timeline, and the effects of the project's changed scope in the next report.
This item has been updated with information from the minutes of the 2026-04-21 meeting.