Major Projects Status Report: Budget, Cancellations, and Delays
The Board of Stockholm Vatten och Avfall AB is recommended to approve a status report for major investment projects exceeding 200 million SEK during the first four months of 2026. The report details the status of 42 projects, noting the cancellation of climate action plans in Bromsten (balancing reservoirs and ponds) and the new recycling center (ÅVC) in Lövsta due to Stockholm Exergi's inability to secure permits for a combined heat and power plant in the area. It also highlights budget deviations in several projects, attributed to factors such as price increases and unexpected geological conditions.
This summary is based on the meeting agenda. We'll update when the minutes are published.