Wastewater Treatment Project Update: Bromma Closure, Henriksdal Expansion
Stockholm Vatten AB is recommended to approve a status report for the Stockholm Future Wastewater Treatment (SFA) project. The report indicates that the project, which includes the closure of the Bromma treatment plant and the expansion of the Henriksdal treatment plant, is on schedule and within budget. The transfer of wastewater from Bromma to Henriksdal is planned for 2028, with the Henriksdal treatment plant to be fully completed in 2031.
This summary is based on the meeting agenda. We'll update when the minutes are published.