Stockholm wastewater project on track for completion in 2031
The board is proposed to approve the progress report on Stockholm’s future wastewater treatment and forward it to Stockholm Vatten och Avfall. The tunnel from Bromma to Sickla and the expansion of the treatment plants in Henriksdal and Sickla are reported to be on track with the revised plan: wastewater is expected to be routed from Bromma to Henriksdal in 2028, and the entire facility is expected to be completed in 2031. The budget is SEK 19.5 billion in 2023 prices, and the forecast is considered to be within the approved budget.
This summary is based on the meeting agenda. We'll update when the minutes are published.