Water and sewer upgrades for Hornsbruksgatan homes
Stockholm Water AB proposes approving an increased budget of SEK 38 million, to a total of SEK 60 million, for a project on Hornsbruksgatan. This is due to unexpectedly large amounts of rock and proximity to the subway, which is delaying the work to renew water and sewer lines for 36 new homes. The project is planned for completion in the third quarter of 2027 and aims to improve the water and sewer supply and reduce the risk of basement flooding in the area.
The original document is available at
meetingspublic.stockholm.se.