Culture & Recreation beslut · Kyrkogårdsnämnden · Meeting 2026-04-15 · Summarized 2026-04-02

Woodland Crematorium Restoration Progress and Budget Update

This report details the ongoing restoration of the culturally significant Woodland Crematorium. Environmental cleanup is complete, groundworks for drainage and excavation are underway, and interior work on ceilings, floors, and walls, including acoustic plaster in the chapels, is progressing. The project is on schedule, but risks remain with the stone facade, hazardous materials, and work on the chapel courtyards; SEK 108.5 million of the SEK 292 million budget has been spent so far.